IT project manager

Help people deliver technical work together. Make scope, progress, decisions and risks clear enough to act on.

Scope and deliveryRisk communicationRelease trade-offs

Try a few exercises

Scope and delivery

Two weeks before launch, a critical feature is requested while testing is incomplete. How would you organize the decision?

Show reference approach
  1. Make benefits, dependencies, risks and scope options explicit for an authorized decision.
  2. Update plans, acceptance criteria and owners; do not hide uncertainty in overtime promises.
Risk communication

A vendor says work is on track but has no acceptable milestone deliverable. How would you verify and report this?

Show reference approach
  1. Verify deliverables, acceptance criteria and dependencies rather than percentages alone.
  2. Report variance, impact, recovery options and the next checkpoint.
More exercises

Related stories

Keep learning

The Open University / OpenLearn

Project management: the start of the project journey

English-language resource

Course reading is free; progress tracking and some activities need a free account.

Scope and costs

Project objectives, risk and planning foundations; not industry certification.

Open free resource